Street work starts, with milling set to begin today, paving Monday

MARQUETTE — As part of Marquette’s ongoing street improvement project, Payne & Dolan Inc. will begin milling today.

Paving will begin on June 5. All work is scheduled to take place under flag control or temporary closure to through traffic, according to a city press release.

The following is a sequence of the planned schedule and the approximate dates for milling and paving.

Milling

≤ Today: Pioneer Road (McClellan west toward waste facility); Third Street (Mather to Fisher); Ridge Street (Sixth to Seventh) and Ohio Street (Front to Third)

≤ Wednesday: Prospect Street (Third to Fourth) Magnetic Street (Front to cul de sac) Park Street (Lee to Seventh)

≤ Thursday: Pine Street (Kaye to Fair and Fair to north of Lakeshore entrance)

≤ Friday: Lincoln Avenue (College to Center)

≤ Monday: Kimber Avenue (Mildred to Fair); Jenny Lane (south end to north end); Huntington Street (Granite to Jenny Lane)

≤ Tuesday, June 4: Wright Street (Ontario to city limits)

≤ Wednesday, June 5: Wright Street (Ontario to city limits); McClellan Avenue (U.S. 41 to Washington)

≤ Thursday, June 6: McClellan Avenue (U.S. 41 to Washington)

Asphalt Paving

≤ Wednesday, June 5: Pioneer Road (McClellan west toward waste facility); Third Street (Mather to Fisher); Ridge (Sixth to Seventh); Ohio (Front to Third)

≤ Thursday, June 6: McClellan Avenue (U.S. 41 to Washington)

≤ Friday, June 7: Wright Street (Ontario to city limits)

≤ Monday, June 10: Wright Street (Ontario to city limits)

≤ Tuesday, June 11: Jenny Lane (south end to north end); Huntington Street (Granite to Jenny Lane); Kimber Avenue (Mildred to Fair); Lincoln Avenue (College to Center)

≤ Wednesday, June 12: Lincoln Avenue (College to Center); Pine Street (Kaye to Fair and Fair to north of Lakeshore entrance)

≤ Thursday, June 13: Magnetic Street (Front Street to cul de sac); Prospect Street (Third to Fourth)

≤ Friday, June 14: Park Street (Lee to Seventh)

The above dates are approximate and due to weather and other circumstances, the milling and paving schedule may shift slightly, according to the city press release.

City officials advise the public to adhere to the temporary “No Parking” signs that will precede the milling and paving.

The milling and paving hours of operation will start around 7 a.m. and continue through 7 p.m., or as needed.