Breaking News
Local

US 41 Houghton improvements to start Sept. 8

By Bud Sargent 2 min read

HOUGHTON -- ­The Michigan Department of Transportation and the city of Houghton are investing about $416,000 in improvements on southbound US 41 (Montezuma Avenue), Bridge Street and Quincy Street to support the future Portage Lake Lift Bridge project. This work will reduce congestion during the upcoming bridge project and create a safer driving environment.

A left-turn lane will be built on Montezuma Avenue and Bridge and Quincy streets will be repaved. A temporary signal is planned to be installed later at the Quincy Street/northbound US 41 (Shelden Avenue) intersection prior to the start of the bridge work.

Once the signal is installed, traffic will be routed from Montezuma Avenue to Shelden Avenue via Bridge and Quincy streets to help with congestion during various phases of the lift bridge project.

Thr tentative starting date for the project is 
Monday, Sept. 8 and the estimated ending date is 
Friday, Oct. 2.

MDOT engineers say motorists should expect lane shifts and a single-lane closure on Montezuma Avenue. Quincy Street is planned to be closed from US 41/Shelden Avenue to the parking decks from Monday, Sept. 21, through Wednesday, Sept. 23.

Bridge Street will be closed from the parking decks to Montezuma Avenue for the duration of the project. All dates are weather dependent.

Starting at /week.