Whitmer freezes EGLE Line 5 tunnel project permits
Trending
LANSING -- Gov. Gretchen Whitmer Tuesday announced that she has directed the Michigan Department of Environment, Great Lakes, and Energy to suspend further action on the resource and pending wastewater permits for the Great Lakes Tunnel Project until legal questions are resolved, according to a state preee release.
“Protecting the Great Lakes and the people who depend on them has been a top priority of mine since day one,” Whitmer said in the press release. “I have always said my ultimate goal is to get Line 5 out of the water. Just one spill threatens irreparable damage to our water, our economy, and our way of life. Given what is at stake, and the Michigan Supreme Court's recent decision, I have directed EGLE to suspend further action on its Line 5 Tunnel Project permits at this time. Michigan will continue to put the protection of our water, environment, public health, and communities first.”
Enbridge spokesman Ryan Duffy responded to The Mining Journal’s request for comment with the following statement: “Since 2018, when the Legislature first established the Mackinac Straits Corridor Authority to oversee construction of a tunnel, Enbridge has worked to secure the approvals needed to relocate Line 5 from the open lakebed into a tunnel beneath the Straits of Mackinac. The Michigan Supreme Court's recent decision to revoke the Michigan Public Service Commission approval has introduced new uncertainty, even as the permitting record remains strong.
“The Michigan Department of Environment, Great Lakes, and Energy issued permits in July 2026 and previously in 2021. Both permitting rounds included detailed technical reviews, public meetings, hearings, and consideration of thousands of public comments. They also involved extensive interaction between Michigan's tribal leaders and state agencies.
“As the cost of everyday essentials, from groceries and clothing to gasoline and home heating, continues to weigh on working families, Line 5 reliably and consistently serves the needs of Michigan and the Great Lakes region by delivering the energy people depend on every day. At Enbridge, we remain committed to that purpose and equally committed to safeguarding the Great Lakes.”
The press release states that Tuesday's action follows the Whitmer's announcement in September that the state must consider the impact of a recent Michigan Supreme Court decision on the resource permits EGLE issued for the proposed Great Lakes Tunnel Project.
EGLE announced its permit decision on July 15. Then, the Michigan Supreme Court issued its decision, In re Application of Enbridge Energy to Replace and Relocate Line 5, which concerned a separate permit issued by the Michigan Public Service Commission in 2023 for the same proposed tunnel beneath the Straits of Mackinac. The Court found the MPSC's review should have included certain environmental harms, vacated the permit the Commission had issued to Enbridge, and remanded the matter back to the MPSC to reconsider the permit application in light of the Court's decision.
The Michigan Supreme Court's decision introduces significant delay and uncertainty. Whitmer’s announcement Tuesday acknowledges this reality and the time it will take for Enbridge to again seek a permit from the MPSC, according to the press release.